First in the series “Profiles of the post-blackout club” — drilldown into each big winner of the Operación Reforzada reshuffle. Next: TotalEnergies at Castejón, Castleton at Amorebieta, and the unifying thesis.
If the unit-level analysis had a relative winner, it was ContourGlobal: +€77M post vs pre, ratio ×27. And its only asset in Spain is Arrubal’s two CCGT units in La Rioja. A single plant, multiplied by nearly 30 in a year, won by an operator few outside the sector have heard of. If you want to understand why Operación Reforzada selects some CCGTs and not others, Arrubal is the clean laboratory.
Who ContourGlobal is — and what it’s doing in La Rioja
ContourGlobal is a mid-sized power generator (~6 GW globally) with assets in a dozen countries. Until 2022 it was LSE-listed; since December 2022 it has been wholly owned by KKR, the US private-equity firm, after a £1.75 billion tender.
In Spain, it operates one single asset: the combined-cycle plant at Arrubal (Logroño, La Rioja). Two gas-turbo blocks, ~400 MW each, ~800 MW total. Connected to the grid via a 220 kV line tying the Ebro-Pyrenees corridor to the rest of the peninsular system. The plant was acquired by ContourGlobal in 2011 from Gas Natural Fenosa (now Naturgy) for €313M — one of the few CCGT asset divestitures Naturgy has made in Spain.
For the operator, Arrubal essentially represents all of its exposure to the Spanish power system. For the Spanish power system, until April 2025, Arrubal was a footnote — a plant running 30-40 hours/month, mostly for residual balancing services or one-off emergencies.
Seven years in hibernation

What the chart shows is striking. From January 2023 through March 2025 — 27 months — Arrubal 1+2’s combined monthly volume in technical-constraints redispatch ranges between 0.04 and 3.9 GWh. The mean is 0.7 GWh/month. Combined dispatch hours: 12 to 50 a month — a handful of sporadic operational incidents.
Pre-blackout prices are the other tell: in most months the average accepted price is €0.1/MWh — the residual market price when the system needs the unit on for technical reasons but its bid was literally zero. The months with meaningful prices (Feb 2023 €36, Oct 2023 €36, Jun 2024 €36, Dec 2024 €65) coincide with specific system events: cold spells, incidents at other units, low-wind windows.
Two anomalous episodes: August 2024 (€2,210/MWh avg at ARRU2) and April 2025 (€2,871/MWh at ARRU1) — those are real scarcity prices, events where REE had to call Arrubal as last resort at prices reflecting scarcity.
The switch (April-May 2025)
The Iberian blackout hits on April 28, 2025. April’s data already shows 3.3 GWh / €2,871 avg — the 2 days post-blackout with emergency activation. But the structural change occurs the following month:
- May 2025: 16.1 GWh, 92 hours, €279/MWh — first week of the new regime
- June 2025: 59.6 GWh, 277 hours, €212/MWh
- September 2025: 63.1 GWh, 293 hours, €204/MWh
- December 2025: 63.9 GWh, 246 hours, €169/MWh
Ten consecutive months with volume 9 to 64 GWh/month (pre-blackout range was 0.04-3.9) and hours 36 to 293 (pre was 12-50). The plant moved from a rare peaker to a semi-continuously dispatched asset.
The key detail: prices fall post-blackout. From pre-blackout volatility (€0.1 to €3,587 depending on the month) to a stable €169-279 band. Operación Reforzada calls Arrubal predictably, enough that the offer can be calibrated to cost-plus-reasonable-margin prices. It’s no longer an emergency peaker; it’s a scheduled asset.

Why Arrubal — the locational thesis
The switch wasn’t because of anything ContourGlobal did. The plant is the same. The turbine is the same. Operating costs are the same. What changed is the criterion REE uses to decide which unit to redispatch post-Operación Reforzada.
Hypothesis: in the Spanish grid, La Rioja sits at the western end of the Aragón-Navarra-Rioja wind corridor, one of the regions with the highest variable-renewable penetration. Aragón alone has 5.5 GW of installed wind (second nationally after Castilla y León); Navarra another 1.6 GW; La Rioja, though smaller, with wind of its own and connected to the Iberdrola-REE Penagos-Cordovilla-Castejón corridor.

When wind ramps up or down (the wind changes, a cloud crosses the PV), the grid needs local synchronous capacity to absorb the fluctuation without collapsing frequency or voltage. Pre-Reforzada criteria let REE manage that variability with fewer synchronous units online at once. Post-Reforzada criteria — stricter, more redundant capacity required — make Arrubal the lowest-cost option to guarantee inertia in the north-interior corridor.
It’s not the only plant in that corridor. The data confirms it: Castejón 3 (TotalEnergies, Navarra), Escatrón 3 (Repsol, Aragón), Castelnou (Engie, Teruel) live parallel dynamics — all of them move from sporadic to semi-continuous use the month of the blackout. That ensemble is the north-interior cluster from the unit analysis.
What sets Arrubal — and ContourGlobal as operator — apart is the symmetry: one plant, one owner, one locational bet. When that bet wins, it wins fully. ContourGlobal is the pure-play of the north-interior cluster.
What this tells us about the next stage of renewable penetration
Three readings:
The economic value of a CCGT depends more on where it is than on who operates it. ContourGlobal has no magic. A 800 MW CCGT in Cádiz (Cartagena 3, Naturgy) lost €37M post-blackout; an identical one in La Rioja gained €77M. The explanatory factor is the node, not the corporate balance sheet.
Expensive peakers are the new losers. Pre-Reforzada, the most profitable per-MWh plants were those earning scarcity prices in a few hours — Besós 5 at €1,400/MWh, As Pontes 5 at €1,945/MWh. Post-Reforzada, REE prefers day-ahead programmed capacity, not last-minute calls. The “emergency peaker” business model is deflating.
Operación Reforzada selects on grid logic, not operator. For the next increments of renewable penetration, the key points are the nodes where variability concentrates: north interior, southwest Andalucía. Whoever has synchronous assets there wins without commercial effort. Whoever has them elsewhere (Galicia, centre, Levante) doesn’t.
ContourGlobal at Arrubal is the cleanest case. In the next post in the series we look at TotalEnergies at Castejón — same trajectory, different node, bigger scale.
The data is open in ESIOS Data — ask about the unit or complex that interests you.
Keep reading
Related articles you might enjoy

Profile #3 — Castleton at Amorebieta: 5 months running at 100%
Third of the post-blackout winners series. Amorebieta (Vizcaya, owned by Castleton Commodities, represented in OMIE by Axpo) operated at saturation — 744 hours/month, the theoretical max — for 5 consecutive months after the blackout. The outlier in the winners club: not 'hibernation → base' like Arrubal, but 'active → 100% all summer → back to normal'. And next door, Bahía de Bizkaia collapses.
Read
Profile #2 — TotalEnergies at Castejón: from rare peaker to base load
Second of the post-blackout winners series. TotalEnergies' Castejón 3 (Navarra) was a rare peaker — under 1 GWh per month at €600+/MWh emergency prices. Post-blackout it runs 27-43 GWh/month at €250/MWh, in line with Arrubal and Escatrón. Three plants, three owners, same grid signal.
Read
Profile #4 — The post-blackout winners club: location dictates, owner ranks
Recap of three profiles (ContourGlobal/Arrubal, TotalEnergies/Castejón, Castleton/Amorebieta) and the unifying thesis: location determines whether a CCGT participates in Operación Reforzada redispatch at all; within a participating cluster, the owner decides whether you win or lose. Renewable-saturated nodes select; the rest of the market is a footnote.
Read