Programming unit · Generación
TMOYGI TMOYGI
Watch this unit- Technology
- Gas Natural Cogeneración
- Capacity
- 19,8 MW
- Agent (market)
- Energya VM · representative CEG
- Owner
- Unresolved
Dispatch by program
daily MWh · I90 arrives ~90 days delayed
Physical units (2)
| UF | Description | Technology | MW |
|---|---|---|---|
| MOYGIRA | MOYGIRA | Gas natural cogeneración | 9,9 |
| MOYZIER | MOYZIER | Gas natural cogeneración | 9,9 |
Linked installations
| Installation | Municipality | Province | MW | Coords |
|---|---|---|---|---|
| ESCOMBRERAS MOYRESA GIRASOL | MURCIA Cartagena | Murcia | 19,9 | 37.5672, -0.9528 |
Recent unavailability
| UF | Start | End | MW available | Cause |
|---|---|---|---|---|
| MOYGIRA | 25 Nov 2018 | 26 Nov 2018 | 1.2 | FAULT |
| MOYZIER | 27 Sept 2017 | 27 Sept 2017 | 0 | FAULT |