Programming unit · Generación

SLTG SALLENT G

Technology
Turbinación bombeo
Capacity
439,2 MW
Agent (market)
Endesa · utility ENDG
Owner
Unresolved

Physical units (4)

UFDescriptionTechnologyMW
SLT4SALLENT 4GTurbinación bombeo109,8
SLT1SALLENT 1GTurbinación bombeo109,8
SLT2SALLENT 2GTurbinación bombeo109,8
SLT3SALLENT 3GTurbinación bombeo109,8

Linked installations

InstallationMunicipalityProvinceMWCoords
ESTANY GENTO-SALLENTE 1LLEIDA Torre de Cabdella, LaLleida439,842.5069, 0.9906

Recent unavailability

UFStartEndMW availableCause
SLT410 Mar 202611 Mar 20260FUEL_LIMITATION
SLT310 Mar 202611 Mar 20260FUEL_LIMITATION
SLT210 Mar 202611 Mar 20260FUEL_LIMITATION
SLT210 Mar 202610 Mar 20260UNKNOWN
SLT37 Mar 20267 Mar 20260FUEL_LIMITATION
SLT27 Mar 20267 Mar 20260FUEL_LIMITATION
SLT15 Mar 202627 Mar 20260SCHEDULED_MAINTENANCE
SLT12 Mar 20262 Mar 20260FAULT
SLT423 Feb 20263 Mar 20260OPERATIONAL
SLT121 Feb 202623 Feb 20260UNKNOWN
SLT118 Feb 202618 Feb 20260UNKNOWN
SLT117 Feb 202617 Feb 20260UNKNOWN
SLT417 Feb 202617 Feb 20260UNKNOWN
SLT217 Feb 202617 Feb 20260UNKNOWN
SLT317 Feb 202617 Feb 20260UNKNOWN
SLT116 Feb 202616 Feb 20260FAULT
SLT216 Feb 202616 Feb 20260FAULT
SLT316 Feb 202616 Feb 20260FAULT
SLT416 Feb 202616 Feb 20260FAULT
SLT413 Feb 202613 Feb 20260OPERATIONAL