Programming unit · Generación
FVLNEVA VLLNA
- Technology
- Solar fotovoltaica
- Capacity
- 42,2 MW
- Agent (market)
- Gesternova · representative GESTE
- Owner
- Unresolved
Physical units (1)
| UF | Description | Technology | MW |
|---|---|---|---|
| VLANEVA | VILLA | Solar fotovoltaica | 42,2 |
Linked installations
| Installation | Municipality | Province | MW | Coords |
|---|---|---|---|---|
| VILLANUEVA | CUENCA Palomares del Campo | Cuenca | 46,8 | 39.9600, -2.6100 |
Recent unavailability
| UF | Start | End | MW available | Cause |
|---|---|---|---|---|
| VLANEVA | 10 Feb 2026 | 10 Feb 2026 | 38.6 | FAULT |
| VLANEVA | 23 Jan 2026 | 23 Jan 2026 | 0 | SCHEDULED_MAINTENANCE |
| VLANEVA | 22 Jan 2026 | 22 Jan 2026 | 0 | UNKNOWN |
| VLANEVA | 13 Jan 2026 | 13 Jan 2026 | 38.6 | UNKNOWN |
| VLANEVA | 12 Jan 2026 | 12 Jan 2026 | 41.6 | UNKNOWN |
| VLANEVA | 22 Dec 2025 | 22 Dec 2025 | 41.6 | UNKNOWN |
| VLANEVA | 21 Dec 2025 | 21 Dec 2025 | 41.6 | UNKNOWN |
| VLANEVA | 11 Dec 2025 | 11 Dec 2025 | 41.6 | UNKNOWN |
| VLANEVA | 27 Nov 2025 | 27 Nov 2025 | 38.6 | UNKNOWN |
| VLANEVA | 24 Nov 2025 | 24 Nov 2025 | 38.6 | UNKNOWN |
| VLANEVA | 24 Nov 2025 | 24 Nov 2025 | 38.6 | UNKNOWN |
| VLANEVA | 18 Nov 2025 | 18 Nov 2025 | 41.6 | UNKNOWN |
| VLANEVA | 29 Oct 2025 | 29 Oct 2025 | 38.6 | UNKNOWN |
| VLANEVA | 28 Oct 2025 | 28 Oct 2025 | 40.4 | FAULT |
| VLANEVA | 27 Oct 2025 | 27 Oct 2025 | 38.6 | UNKNOWN |
| VLANEVA | 23 Oct 2025 | 23 Oct 2025 | 27.7 | UNKNOWN |
| VLANEVA | 20 Oct 2025 | 20 Oct 2025 | 31.4 | FAULT |
| VLANEVA | 15 Sept 2025 | 19 Sept 2025 | 38.6 | UNKNOWN |
| VLANEVA | 12 Sept 2025 | 12 Sept 2025 | 38.6 | UNKNOWN |
| VLANEVA | 12 Sept 2025 | 12 Sept 2025 | 38.3 | UNKNOWN |