Programming unit · Generación
EMAJOGA PE MAJOGAZ
- Technology
- Eólica
- Capacity
- 49,5 MW
- Owner
- Unresolved
Physical units (1)
| UF | Description | Technology | MW |
|---|---|---|---|
| MAJOGAZ | MAJOGAZ | Eólica | 49,5 |
Linked installations
| Installation | Municipality | Province | MW | Coords |
|---|---|---|---|---|
| P.E. MAJOGAZAS | ALBACETE Masegoso | Albacete | 49,5 | 38.6844, -2.3017 |
Recent unavailability
| UF | Start | End | MW available | Cause |
|---|---|---|---|---|
| MAJOGAZ | 17 Feb 2026 | 19 Feb 2026 | 37.5 | UNKNOWN |
| MAJOGAZ | 15 Feb 2026 | 16 Feb 2026 | 41.5 | UNKNOWN |
| MAJOGAZ | 14 Feb 2026 | 15 Feb 2026 | 30 | UNKNOWN |
| MAJOGAZ | 13 Feb 2026 | 14 Feb 2026 | 31.5 | UNKNOWN |
| MAJOGAZ | 13 Feb 2026 | 13 Feb 2026 | 34.5 | UNKNOWN |
| MAJOGAZ | 11 Feb 2026 | 12 Feb 2026 | 36 | UNKNOWN |
| MAJOGAZ | 10 Feb 2026 | 11 Feb 2026 | 47 | UNKNOWN |
| MAJOGAZ | 9 Feb 2026 | 10 Feb 2026 | 37.5 | COMMERCIAL |
| MAJOGAZ | 5 Feb 2026 | 5 Feb 2026 | 33.5 | COMMERCIAL |
| MAJOGAZ | 5 Feb 2026 | 5 Feb 2026 | 16.5 | COMMERCIAL |
| MAJOGAZ | 26 Jan 2026 | 26 Jan 2026 | 25.6 | UNKNOWN |
| MAJOGAZ | 24 Jan 2026 | 25 Jan 2026 | 25.6 | UNKNOWN |
| MAJOGAZ | 24 Jan 2026 | 24 Jan 2026 | 25.6 | UNKNOWN |
| MAJOGAZ | 20 Nov 2025 | 20 Nov 2025 | 0 | UNKNOWN |
| MAJOGAZ | 7 Oct 2025 | 7 Oct 2025 | 0 | UNKNOWN |
| MAJOGAZ | 20 Aug 2025 | 20 Aug 2025 | 0 | UNKNOWN |
| MAJOGAZ | 15 Feb 2025 | 15 Feb 2025 | 0 | UNKNOWN |
| MAJOGAZ | 14 Feb 2025 | 14 Feb 2025 | 0 | UNKNOWN |
| MAJOGAZ | 13 Feb 2025 | 13 Feb 2025 | 0 | UNKNOWN |
| MAJOGAZ | 24 Dec 2024 | 24 Dec 2024 | 0 | UNKNOWN |