Programming unit · Generación
EEGPE1 EEGPE1
- Technology
- Eólica
- Capacity
- 175 MW
- Owner
- Unresolved
Physical units (2)
| UF | Description | Technology | MW |
|---|---|---|---|
| CAMPIL3 | CAMPIL3 | Eólica | 87,5 |
| CAMPIL2 | CAMPIL2 | Eólica | 87,5 |
Recent unavailability
| UF | Start | End | MW available | Cause |
|---|---|---|---|---|
| CAMPIL3 | 23 Feb 2026 | 27 Feb 2026 | 0 | UNKNOWN |
| CAMPIL2 | 23 Feb 2026 | 27 Feb 2026 | 0 | UNKNOWN |
| CAMPIL2 | 16 Feb 2026 | 20 Feb 2026 | 73.5 | SCHEDULED_MAINTENANCE |
| CAMPIL3 | 27 Jan 2026 | 27 Jan 2026 | 0 | SCHEDULED_MAINTENANCE |
| CAMPIL2 | 27 Jan 2026 | 27 Jan 2026 | 0 | SCHEDULED_MAINTENANCE |
| CAMPIL2 | 7 Nov 2025 | 7 Nov 2025 | 75.3 | INSPECTION |
| CAMPIL2 | 6 Nov 2025 | 6 Nov 2025 | 75.3 | INSPECTION |
| CAMPIL2 | 5 Nov 2025 | 5 Nov 2025 | 75.3 | INSPECTION |
| CAMPIL2 | 4 Nov 2025 | 4 Nov 2025 | 75.3 | INSPECTION |
| CAMPIL2 | 29 Aug 2025 | 29 Aug 2025 | 73.5 | SCHEDULED_MAINTENANCE |
| CAMPIL2 | 28 Aug 2025 | 28 Aug 2025 | 73.5 | SCHEDULED_MAINTENANCE |
| CAMPIL2 | 27 Aug 2025 | 27 Aug 2025 | 73.5 | SCHEDULED_MAINTENANCE |
| CAMPIL2 | 26 Aug 2025 | 26 Aug 2025 | 73.5 | SCHEDULED_MAINTENANCE |
| CAMPIL2 | 25 Aug 2025 | 25 Aug 2025 | 73.5 | SCHEDULED_MAINTENANCE |
| CAMPIL3 | 22 Aug 2025 | 22 Aug 2025 | 61 | INSPECTION |
| CAMPIL2 | 22 Aug 2025 | 22 Aug 2025 | 73.5 | SCHEDULED_MAINTENANCE |
| CAMPIL3 | 21 Aug 2025 | 21 Aug 2025 | 61 | INSPECTION |
| CAMPIL2 | 21 Aug 2025 | 21 Aug 2025 | 73.5 | SCHEDULED_MAINTENANCE |
| CAMPIL2 | 20 Aug 2025 | 20 Aug 2025 | 73.5 | SCHEDULED_MAINTENANCE |
| CAMPIL2 | 19 Aug 2025 | 19 Aug 2025 | 73.5 | SCHEDULED_MAINTENANCE |