Programming unit · Generación
ECYLEO ECYLEO
- Technology
- Eólica
- Capacity
- 140,6 MW
- Owner
- Unresolved
Physical units (3)
| UF | Description | Technology | MW |
|---|---|---|---|
| ZAPATER | ZAPATER | Eólica | 49,4 |
| ELGALLO | ELGALLO | Eólica | 49,4 |
| PEZARZU | PEZARZU | Eólica | 41,8 |
Recent unavailability
| UF | Start | End | MW available | Cause |
|---|---|---|---|---|
| ZAPATER | 7 Jan 2026 | 20 Jan 2026 | 0 | COMMERCIAL |
| PEZARZU | 7 Jan 2026 | 20 Jan 2026 | 0 | COMMERCIAL |
| ELGALLO | 7 Jan 2026 | 20 Jan 2026 | 0 | COMMERCIAL |
| ELGALLO | 25 Aug 2025 | 29 Aug 2025 | 0 | COMMERCIAL |
| ZAPATER | 25 Aug 2025 | 29 Aug 2025 | 0 | COMMERCIAL |
| PEZARZU | 25 Aug 2025 | 29 Aug 2025 | 0 | COMMERCIAL |
| PEZARZU | 28 Jul 2025 | 31 Jul 2025 | 0 | OPERATIONAL |
| ZAPATER | 28 Jul 2025 | 31 Jul 2025 | 0 | OPERATIONAL |
| ELGALLO | 28 Jul 2025 | 31 Jul 2025 | 0 | OPERATIONAL |
| ZAPATER | 29 Jun 2025 | 4 Jul 2025 | 0 | COMMERCIAL |
| ELGALLO | 29 Jun 2025 | 4 Jul 2025 | 0 | COMMERCIAL |
| PEZARZU | 29 Jun 2025 | 4 Jul 2025 | 0 | COMMERCIAL |
| ELGALLO | 17 Dec 2024 | 31 Jan 2025 | 0 | COMMERCIAL |
| ZAPATER | 17 Dec 2024 | 31 Jan 2025 | 0 | COMMERCIAL |
| PEZARZU | 17 Dec 2024 | 31 Jan 2025 | 0 | COMMERCIAL |
| ELGALLO | 10 Jun 2024 | 15 Jun 2024 | 0 | SCHEDULED_MAINTENANCE |
| ZAPATER | 10 Jun 2024 | 15 Jun 2024 | 0 | SCHEDULED_MAINTENANCE |
| PEZARZU | 10 Jun 2024 | 15 Jun 2024 | 0 | SCHEDULED_MAINTENANCE |
| ELGALLO | 25 Oct 2023 | 25 Oct 2023 | 0 | COMMERCIAL |
| ZAPATER | 19 May 2023 | 6 Jun 2023 | 0 | COMMERCIAL |