Programming unit · Generación
COGATOM COGATOM
- Technology
- Gas Natural Cogeneración
- Capacity
- 5,5 MW
- Owner
- Unresolved
Physical units (1)
| UF | Description | Technology | MW |
|---|---|---|---|
| ATOMIZZ | UF_ATOMIZA | Gas natural cogeneración | 5,5 |
Linked installations
| Installation | Municipality | Province | MW | Coords |
|---|---|---|---|---|
| ATOMIZADORA | CASTELLÓN/CASTELLÓ Onda | Castellón | 5,5 | 39.9700, -0.2403 |
Recent unavailability
| UF | Start | End | MW available | Cause |
|---|---|---|---|---|
| ATOMIZZ | 23 Feb 2026 | 30 Apr 2026 | 0 | SCHEDULED_MAINTENANCE |
| ATOMIZZ | 3 May 2024 | 6 May 2024 | 0 | FAULT |
| ATOMIZZ | 16 Apr 2024 | 16 Apr 2024 | 0 | UNKNOWN |
| ATOMIZZ | 16 Dec 2023 | 20 Dec 2023 | 0 | SCHEDULED_MAINTENANCE |
| ATOMIZZ | 1 Nov 2023 | 3 Nov 2023 | 0 | SCHEDULED_MAINTENANCE |
| ATOMIZZ | 21 Oct 2023 | 30 Oct 2023 | 0 | SCHEDULED_MAINTENANCE |
| ATOMIZZ | 7 Oct 2023 | 13 Oct 2023 | 0 | SCHEDULED_MAINTENANCE |
| ATOMIZZ | 30 Aug 2023 | 4 Sept 2023 | 0 | UNKNOWN |
| ATOMIZZ | 25 Aug 2023 | 28 Aug 2023 | 0 | SCHEDULED_MAINTENANCE |
| ATOMIZZ | 7 Aug 2023 | 18 Aug 2023 | 0 | SCHEDULED_MAINTENANCE |