Programming unit · Generación
TSEAT COGE SEAT
- Technology
- Gas Natural Cogeneración
- Capacity
- 22,8 MW
- Owner
- Unresolved
Physical units (1)
| UF | Description | Technology | MW |
|---|---|---|---|
| TSEAT | SEAT | Gas natural cogeneración | 22,8 |
Linked installations
| Installation | Municipality | Province | MW | Coords |
|---|---|---|---|---|
| CG SEAT | BARCELONA Martorell | Barcelona | 21,8 | 41.8403, 2.5039 |
Recent unavailability
| UF | Start | End | MW available | Cause |
|---|---|---|---|---|
| TSEAT | 30 Apr 2025 | 5 May 2025 | 0 | COMMERCIAL |
| TSEAT | 4 Aug 2024 | 31 Aug 2024 | 0 | SCHEDULED_MAINTENANCE |
| TSEAT | 31 Mar 2024 | 5 Apr 2024 | 0 | SCHEDULED_MAINTENANCE |
| TSEAT | 19 Nov 2023 | 20 Nov 2023 | 0 | COMMERCIAL |
| TSEAT | 1 Nov 2023 | 5 Nov 2023 | 0 | COMMERCIAL |
| TSEAT | 16 Oct 2023 | 23 Oct 2023 | 0 | SCHEDULED_MAINTENANCE |
| TSEAT | 13 Oct 2023 | 16 Oct 2023 | 0 | COMMERCIAL |
| TSEAT | 29 Dec 2021 | 29 Dec 2021 | 0 | SCHEDULED_MAINTENANCE |
| TSEAT | 19 Aug 2021 | 19 Aug 2021 | 0 | FAULT |
| TSEAT | 18 Aug 2021 | 19 Aug 2021 | 0 | OPERATIONAL |
| TSEAT | 24 Jul 2021 | 26 Jul 2021 | 0 | OPERATIONAL |
| TSEAT | 15 May 2021 | 15 May 2021 | 0 | FAULT |
| TSEAT | 30 Apr 2021 | 1 May 2021 | 0 | OPERATIONAL |
| TSEAT | 20 Mar 2021 | 21 Mar 2021 | 0 | FAULT |
| TSEAT | 20 Feb 2021 | 21 Feb 2021 | 6.5 | UNKNOWN |
| TSEAT | 1 Feb 2021 | 1 Feb 2021 | 8 | OPERATIONAL |
| TSEAT | 30 Jan 2021 | 31 Jan 2021 | 7 | OPERATIONAL |
| TSEAT | 27 Nov 2020 | 27 Nov 2020 | 0 | SCHEDULED_MAINTENANCE |
| TSEAT | 9 Nov 2020 | 12 Nov 2020 | 0 | FAULT |
| TSEAT | 1 Aug 2020 | 29 Aug 2020 | 0 | SCHEDULED_MAINTENANCE |