Programming unit · Generación
PGR5 P.G.RODR 5
- Technology
- Ciclo combinado
- Capacity
- 855,6 MW
- Owner
- Unresolved
Physical units (3)
| UF | Description | Technology | MW |
|---|---|---|---|
| PGR5TV | PGR5TV | Vapor | 302,7 |
| PGR5TG1 | PGR5TG1 | Ciclo combinado | 276,6 |
| PGR5TG2 | PGR5TG2 | Ciclo combinado | 276,3 |
Linked installations
| Installation | Municipality | Province | MW | Coords |
|---|---|---|---|---|
| CCGT AS PONTES GARCIA RODRIGUEZ 5 TG1 | A CORUÑA Pontes de García Rodríguez, As | A Coruña | 855,7 | 43.4416, -7.8605 |
Recent unavailability
| UF | Start | End | MW available | Cause |
|---|---|---|---|---|
| PGR5TV | 5 Mar 2026 | 3 May 2026 | 124 | FAULT |
| PGR5TV | 4 Mar 2026 | 5 Mar 2026 | 124 | FAULT |
| PGR5TV | 4 Mar 2026 | 4 Mar 2026 | 0 | FAULT |
| PGR5TG2 | 4 Mar 2026 | 4 Mar 2026 | 0 | FAULT |
| PGR5TV | 4 Mar 2026 | 4 Mar 2026 | 124 | FAULT |
| PGR5TV | 20 Feb 2026 | 3 Mar 2026 | 124 | FAULT |
| PGR5TV | 10 Jan 2026 | 19 Feb 2026 | 151.3 | FAULT |
| PGR5TG2 | 10 Jan 2026 | 10 Jan 2026 | 0 | UNKNOWN |
| PGR5TV | 10 Jan 2026 | 10 Jan 2026 | 0 | UNKNOWN |
| PGR5TV | 1 Jan 2026 | 10 Jan 2026 | 151.3 | FAULT |
| PGR5TG1 | 1 Jan 2026 | 31 Jan 2027 | 0 | FAULT |
| PGR5TG1 | 22 Dec 2025 | 31 Dec 2025 | 0 | FAULT |
| PGR5TV | 17 Dec 2025 | 31 Dec 2025 | 151.3 | FAULT |
| PGR5TG1 | 30 Nov 2025 | 21 Dec 2025 | 0 | FAULT |
| PGR5TV | 30 Nov 2025 | 17 Dec 2025 | 0 | FAULT |
| PGR5TG2 | 30 Nov 2025 | 17 Dec 2025 | 0 | FAULT |
| PGR5TV | 1 Nov 2025 | 5 Nov 2025 | 0 | INSPECTION |
| PGR5TG1 | 1 Nov 2025 | 5 Nov 2025 | 0 | INSPECTION |
| PGR5TG2 | 1 Nov 2025 | 5 Nov 2025 | 0 | INSPECTION |
| PGR5TV | 15 Oct 2025 | 16 Oct 2025 | 151.4 | FAULT |